Khorezm regions, Urganch district, Uyshin mahalla

Construction of a 150-bed preschool educational institution in Uyshin MCA
Project description

There is no kindergarten in the Uishin community. The total number of children from 3 to 6 years old is 266 children. The population of the community needs a kindergarten for the preschool development of children. But there is no free space for the construction of a new kindergarten on the territory of Uishin. Therefore, the construction is planned to be built on the neighboring Merganovul community next to school No. 7. After the commissioning of the cluster facility, the children of both Uishin and Merganovul mahallas will be able to attend this kindergarten.


At this facility, excavation work was completed by 100%, and foundation work by 70%.

Information about the sub project
In progress

15%

Completeness (percentage)

In progress

Project status

0/5

Grade
State before the project and after the project
Before the project implementation
Project implementation process
After the project is done